TM announced a key production milestone, having mined 980tpd over a 30-day period, surpassing a threshold in the Sprott streaming agreement.
This news de-risks the project as Trigon is no longer required to convert the principal advance into a loan (more detail below).
As a result of the highly successful underground mining operations, the Company has decided to pause the open pit and only process high-grade underground ore.